
        Case Study
: Hardline for Ashok Leyland Component Test Lab Bay 2: Chennai, INDIA
        
        Project No: 3677
After successfully executing the hydraulic  piping/hardline for the New Component Test Lab Bay 1, there was a requirement  of expansion of the hardline for the New Component Test Lab Bay 2. Ashok  Leyland again handed this responsibility to Chase Resource. A leading Testing  & Sensing Equipment OEM’s was providing all the necessary Test equipment’s  and the same was to be integrated viz. the HPUs and Actuators.   
        
        The Project key points are as follows:
        
        - Implementation of large bore Non Welded Hydraulic / High Pressure / Hardline Piping system for the Component Test Lab Actuators
- Implementation       of hardline piping and supporting structure to withstand high vibrations       of the testing machines (upto 50 Hz)
-  Issuance of all the drawings prior to installation. The installation process was based on pre- designed & pre-fabricated Hardline Pipe spools.
-  Pipes were pre-fabricated and they were carefully laid out in a defined space - meeting the
            design & schematic layout criteria.
The various steps involved were as follows 
        
          - Design / Engineering: Since this was a project involving Hardline  Piping for a test lab, prior design could be carried out. The end user had  defined their requirement to which we proposed suitable piping specifications.  The design was entirely carried out in-house  based on necessary information like Hydraulic Schematic Drawing, Civil Layout,  and RC Detail Drawing. The Hardline Piping design once issued was accepted by  the End-User to suit the final application delivery.  
- 
         Fabrication: The       Hardline Piping involved in this project were all pre-designed and       pre-fabricated since site layout details were accurately available at our       end. All the spools were pre-fabricated, cleaned, painted in TMI facility       in Canada and shipped to the site. These above methods are employed so       that the hardlines do not get contaminated by dirt, dust, rust, pollution       during transportation & handling, which could hamper the final Hydraulic       application.        
-  Erection: All the Hardline Piping was erected under the supervision of Chase Resource
            Supervisors and Technicians. The erection had to be carried out carefully since the
          cleanliness requirement at the lab was of top priority.  
-  Flushing: The Hardline was looped by Chase Resource Flushing components and flushed. We
            achieved a “NAS 0” cleanliness level which was applauded by the End-User. It hardly took
            half a day to achieve the above cleanliness level which clearly demonstrates the merit of
          using Non Welded Piping for such particular Testing Applications.
-  Pressure Testing: The Hardline had to be pressure / proof tested up to 4500 psi. The above
            pressure rating was subjected on the Hardline and was held for 30 min (standard states hold
          time of 15 mins is sufficient).
-  Commissioning: After the installation phase the Hardline was ready to be commissioned.
            All the Simulation actuators / equipment’s are tested by the end user and the lab has been
          operational from last year itself. 
-  Hand Over: After successful commissioning, all the spares, documentation, reports were
            handed over to the End-User and a copy was kept with Chase Resource for future reference
            & traceability. The same was provided in digital format for easy access.  
        Chase Resource will soon be executing another similar hydraulic hardline installation project for  Ashok Leyland in the near future.